Installation of Access

Installation of Access Doors in Ventilation Ducting
1  Operatives to check all PPE, cleaning equipment and chemicals required for the task. Refer to COSHH assessments supplied for chemicals being used. Operatives to set out all ‘Caution/Warning’ signage required and cordon off cleaning area prior to work commencing.
2  Only trained operatives are allowed to carry out this task.
3  Operatives to ensure that if a ‘Permit to Work’ system is in place, that it is read, understood and signed by those undertaking the task.
4  Operatives to carry out survey of ducting to determine best area for access panel to be fitted.
5  Operatives to erect the necessary access equipment, step ladders or ladders (note where possible tops of ladders should be placed on to a solid surface).
6  Operatives to mark the cutting edge of access door using the template supplied.
7  Operatives to coat along the cutting edge with lubricant.